Mount Hope Townhouse

Mount Hope Townhouse

Architect: Manhatta Architecture, P.C. (Bronx, NY)

Mechanical Engineer: RHL Engineering, LLC (Scotch Plains, NJ)

Structural Engineer: A Valerio Building Consultants Inc (Mahopac, NY)

General Contractor: Killowen Construction (Brooklyn, NY)

Mechanical Contractor: Gazz HVAC Inc. (Astoria, NY)

Plumbing Contractor: Hunter Mechanical (Yonkers, NY)

Electrical Contractor: Gotham Wiring Inc. (Bronx, NY)

Tiler: Causeway Tile and Marble Inc (Bronx, NY)

Floor Refinisher: Wood Woodpecker Hardwood Floors (Mount Vernon, NY)

T.103.00-Row Plan.jpg
Parlor-Scope of Work

Parlor-Scope of Work

Floors: (1) Repair damaged parquet border and field. (2) Cut openings for forced air HVAC and floor receptacles (3) Sand and refinish.

Walls & Ceiling: (1) Patch and repair and bring to Level 5 finish.  (2) Replace ceiling medallion.

Trimwork and Millwork: Strip and Re-finish existing mahogany trimwork and millwork.

Lighting & Electrical: (1) Replace all wiring.  (2) New receptacles spaced per current electrical code. (3) New ceiling fan with digital dimmer.

113East179thStreetTH_Richard_Garey_ManhattaArchitecture_Photography_49733860_high_res-REVISED.jpg
Dining Room-Scope of Work

Dining Room-Scope of Work

Floors: (1) Repair termite & water damaged joists and subfloor below existing parquet. (2) Repair damaged parquet border and field. Shift east border to accomodate proposed bathroom (3) Cut openings for floor receptacles (4) Sand and refinish

Walls & Ceiling: (1) Demo and replace ceiling.  (2) Patch and repair walls. Bring plaster surfaces to Level 5 finish.  (3) Replace ceiling medallion.

Fenestration: Replace existing oversized double-hung window with french doors leading to terrace.

Trimwork: (1) Shift east border to accomodate proposed bathroom (2) Repair damage from defunct radiant heating system (3) Provide new step incorporating ducting of HVAC stem.  (4) Match historic millwork profiles for restoration elements (5) Provide new stain grade crown moulding using historic trimwork salvaged from Tulnoy Lumber in Bronx, NY. (6) Strip and refinish existing white oak trimwork.

Lighting & Electrical: (1) Replace all wiring.  (2) New receptacles spaced per current electrical code. (3) New ceiling fan with digital dimmer.

113East179thStreetTH_Richard_Garey_ManhattaArchitecture_Photography_49734522_high_res-REVISED.jpg
Bathroom-Scope of Work

Bathroom-Scope of Work

NOTE: Full bathroom relocated from 3rd floor to 1st floor to accomodate disabled client.

Floors: New tile flooring throughout

Walls & Ceiling: New tile and beadboard throughout  

Millwork: New vanity, sink and faucet.

Lighting & Electrical: (1) Replace all wiring.  (2) New receptacles spaced per current electrical code. (3) New Lighting.  

Combined Bathroom.jpg
Kitchen-Scope of Work

Kitchen-Scope of Work

Floors: (1) Repair and replace deteriorated joists and subfloor. (2) Install tile underlayment (3) Install hand-made Arto tile sourced from Los Angeles.

Walls & Ceiling: (1) Strip existing plaster to expose brick.  Repair & Re-point masonry as required (2) Install tile backsplash using salvaged historic tile Demo and replace ceiling.  (3) Demo and replace ceiling.  Bring plaster surface to Level 5 finish.  

Fenestration: Replace windows.

Millwork: (1) Demo and replace millwork (2) New custom concrete countertop by Trueform Concrete of Denville, New Jersey.

Lighting & Electrical: (1) Replace all wiring.  (2) New receptacles spaced per current electrical code. (3) New Lighting.  (4) New appliances.